Ethel Street ATC Phase 5
2020 | Kelowna, BC
McElhanney acted as the coordinating professional and civil engineers of record for the 5th phase of the City’s Ethel Street Active transportation Corridor – an important north-south link in the City’s ATC network plan.
The project included 400m of 250mm dia. watermain replacement and roadway improvements including the addition of one-way protected cycle tracks, curbing, sidewalk, landscaping and streetlighting.
McElhanney’s Kelowna team provided:
- Detailed engineering design
- Project procurement / tendering services
- Construction and contract administration services
![Ethel Street Intersection Ethel Street Intersection](https://www.mcelhanney.com/wp-content/uploads/2021/04/174423894_1361436114218241_1100316348720023572_n_small.jpg)
![Ethel Street Separated Bike Lane Ethel Street Separated Bike Lane](https://www.mcelhanney.com/wp-content/uploads/2021/04/174446575_800275530924493_7718156393036409842_n.jpg)
![Ethel Intersection Ethel Intersection](https://www.mcelhanney.com/wp-content/uploads/2021/04/174452792_936129293810661_8582885181761870039_n.jpg)