2020 | Kelowna, BC

McElhanney acted as the coordinating professional and civil engineers of record for the 5th phase of the City’s Ethel Street Active transportation Corridor – an important north-south link in the City’s ATC network plan.

The project included 400m of 250mm dia. watermain replacement and roadway improvements including the addition of one-way protected cycle tracks, curbing, sidewalk, landscaping and streetlighting.

McElhanney’s Kelowna team provided:

  • Detailed engineering design
  • Project procurement / tendering services
  • Construction and contract administration services